For tree plantation 30 workers dig 20 pits in 40 days if 40 workers have to dig 30 pits how many days will be required ??
Answers
Answered by
2
Answer:
20 days is the answer (inverse proportion)
Step-by-step explanation:
hope it help you
Answered by
0
Answer:
x=24½ days Required
Step-by-step explanation:
30*20*49=40*30*x
29,400=1200*x
x=29,400/1200
x=24½ days Required