Fourteen persons can do a work in 18 days . After 5 days of work , 6 workers left the work , and joined back on the last day of the work . In how many days the work got completed
Answers
Solution :-
Let us assume that, each person can do 1 unit of work per day .
So,
→ 14 person can do = 1 * 14 = 14 units / day
then,
→ In 18 days 14 person can do = 18 * 14 = 252 units = Total work .
Now,
→ In first 5 days , 14 persons completed = 5 * 14 * 1 = 70 units .
and,
→ In last day, 14 persons completed = 1 * 14 * 1 = 14 units .
then,
→ Total work completed in 6 days = 70 + 14 = 84 units .
Now,
→ Left work to be done = 252 - 84 = 168 units
and,
→ Left person = 14 - 6 = 8 persons .
therefore,
→ Time taken by 8 person to complete left work = 168/(8 * 1) = 21 days .
hence,
→ Time taken to complete the work = 5 + 21 + 1 = 27 days (Ans.)
∴ The work got completed in 27 days .
Learn more :-
Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...
https://brainly.in/question/21025557
Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...
https://brainly.in/question/14687371
Work done 14 men*6days
Remaining work 14men*12=14-6) men* days=21