From the following records of Bonuscrew Ltd., you are
required to compute the material and labour variances :
1 tonne of material yields a standard output of 1 lakh
units.
Number of employees is 200
The standard wage rate per employee per day is Rs. 6.
Standard price of material is Rs. 20 per kg.
Actual quantity of material issued by production
department 10 tonnes.
Actual price of material is Rs. 21 per kg.
Actual output is 9 lakh units.
Actual wage rate per day is Rs. 6.50.
Standard daily output per employee is 100 units.
Total number of days worked is 50.
Idle time paid for and included above is 1/2 day.