Given the expected completion time for an activity is 12 days.
Calculate the standard deviation of the activity if the optimistic time
is 9 days and the most likely time is 10 days.
A) 2- days
3
2
B) 2= days
3
2
C) 15 days
3
c
1
D) 3= days
2