Henry can complete 5/8 of a job 15 days. how long will he take to complete the entire job?
Answers
Answered by
1
Answer:
24 days
Step-by-step explanation:
1 job completed in 15/5 days=3 days
8 job completed in 3*8 days=24 days
in 24 days all the jobs where completed