Hey !!!!! please help me out !!!!
A contractor employed 210 men to build a house in 60 days . After 12 days ,he was joined by 70 more men . In how many days will the remaining work be finished ???
Answers
Answered by
2
hlo your answer..✨✨✨✨
210 men can built house in 60 days
after 12 day 70 men joind
total man = 210 + 70 = 280
days left = 60 - 12 = 48
so, 210 men can bulit wall in 48 days...
then 280 men can built wall in x day
in case of inverse proportin
210 × 48 = 280 × x
x = 210 × 48 / 280
x = 10080 / 280
x = 36 days..
hope it helps...
please mark as brainly...✨✨
210 men can built house in 60 days
after 12 day 70 men joind
total man = 210 + 70 = 280
days left = 60 - 12 = 48
so, 210 men can bulit wall in 48 days...
then 280 men can built wall in x day
in case of inverse proportin
210 × 48 = 280 × x
x = 210 × 48 / 280
x = 10080 / 280
x = 36 days..
hope it helps...
please mark as brainly...✨✨
Answered by
1
36 days
hope it helps you