5. A contract on construction job specifies a penalty
for delay of completion beyond a certain date
as follows : 200 for the first day, * 250 for
the second day, 300 for the third day, etc.,
the penalty for each succeeding day being 50
more than for the preceding day. How much
money the contractor has to pay as penalty, if
he has delayed the work by 30 days?
Answers
Answered by
3
Answer:
Ans: Is S30= 27750..
please mark as brainlist answer....