How does an agile team obtain clarity on backlog items that may be picked up in upcoming iterations ?

A) During iteration planning team discusses backlog items for both current and upcoming iterations

B) Product Owner and Facilitator detail out the backlog items planned for upcoming iterations

C) There is no need to obtain clarity on backlog items for upcoming iterations in advance

D) During every iteration, team has backlog refinement session with the Product Owner for gaining clarity on the backlog items to be picked up in the upcoming iterations

Answers

Answered by ankurbadani84
25

Answer:

During every iteration, team has backlog refinement session with the Product Owner for gaining clarity on the backlog items to be picked up in the upcoming iterations

Explanation:

In iteration planning, team with PO collectively decides how much of backlog they can commit to an iteration. That committed backlog is then taken to delivery in next iteration. Based on committed work, goals of iteration are determined.