How long will 50 men take to do the same job, that 40 men do in 25 days
Answers
Answered by
32
Answer:
50 men will take 20 days to do the work.
Step-by-step explanation:
The given problem is
Men Time (days)
40 25
50 ?
We know that 'Men' and 'Time' are inversely proportional because when number of men increases, amount of time decreases, vice versa.
Hence required amount of time
= (40 × 25) / 50 days
= 20 days
Therefore 50 men will take 20 days to do the work.