How to calculate total work time available for scrum team?
Answers
Answered by
0
Answer:
Explanation:
Multiply the number of workdays in the period by eight (hours per day) to get the total number of “Work Hours” hours in the period. Subtract the total time allocated for whole-team meetings. This result is the “Net Work Hours,” and is smaller than the total “Work Hours.”