(i) Sunil takes 5 days more than Anil to complete a certain work. 4 days after starting
the work, Anil left the work. The remaining work was done by Sunil in 5 days.
Find how many days each will take to complete the work.
Answers
Sunil takes 5 days more than Anil to complete a certain work. 4 days after startingvthe work, Anil left the work. The remaining work was done by Sunil in 5 days. Find how many days each will take to complete the work.
Let Anil takes x number of days to complete the work.
1 day = 1 / x of the work
Sunil takes 5 more days than Anil to complete the work.
x + 5 days
1 day = 1 / (x + 5) of the work
★ Together:-
1 day = 1 / x + 1 / (x + 5)
1 day = (x + 5 + x) / x (x + 5)
1 day = (2x + 5) / (x² + 5x) of work done
★ To find 4 days of work done:-
1 day = (2x + 5) / (x² + 5x)
4 days = 4 (2x + 5) / (x² + 5x)
4 days = (8x + 20) / (x² + 5x) of work done.
★ To find the amount of work left to be done:-
Work left = 1 - (8x + 20) / (x² + 5x)
Work left = (x² + 5x - 8x - 20) / (x² + 5x)
Work left = (x² - 3x - 20) / (x² + 5x)
★ Point to remember:-
Given that Anil needs 5 days to complete the rest of the work.
(x² - 3x - 20) / (x² + 5x) ÷ 1 / (x + 5) = 5
(x² - 3x - 20) / (x² + 5x) × (x + 5) = 5
(x² - 3x - 20) / x = 5
x² - 3x - 20 = 5x
x² - 8x - 20 = 0
(x - 10) (x + 2) = 0
x = 10 or x = - 2 (Number of days cannot be negative)
Therefore, x = 10.
★ To find the number of days each take to complete the work:-
Anil =
Sunil = x + 5 = 10 + 5 = 15
Hence, Anil takes 10 days and Sunil takes 15 days to complete the work.
__________________________________
Number of days taken by Anil to complete the work = 10 days
Number of days taken by Sunil to complete the work = 15 days
GiVeN :
- Sunil takes 5 days more than Anil to complete a certain work.
- 4 days after startingthe work, Anil left the work.
- The remaining work was done by Sunil in 5 days
To FiNd :
- Number of days taken by Sunil and Anil to complete the work individually.
SoLuTiOn:
Let the number of days taken by Anil to complete the work be x.
---> (1)
- Sunil takes 5 days more than Anil to complete a certain work.
---> (2)
- 4 days after starting
- 4 days after startingthe work, Anil left the work.
Anil's + Sunil's work :
+
4 days work :
To find the work completed in 4 days we can simply multiply one day's work by 4,
Now given given that,
- Anil left the work
So amount of work remaining will be difference of 4 day's work and one
Remaining work was done :
Sunil completed the remaining work in 5 days.
Constituting it mathematically,
÷ = 5
= 5
= 5
• Calculation from the website :
- Wolframalpha
x = - 2 is not acceptable since the number of days cannot be negative.
•°• Number of days taken by Anil to complete the work individually = 10 days.
Number of days taken by Sunil,
•°• Sunil took 15 days to complete the work individually.