If 10 men can complete a work in 6 days then 30 men can complete the same work in how many days
Answers
Answered by
15
Answer:2 days
Step-by-step explanation:
Let the no. Of days be x.
A.T.Q.
10*6=30*x
x=10*6/30
x=2 days
Answered by
10
Answer
2 days
Step by Step explanation
If 'x' men takes 'y' days to complete a given work, 1 man would take 'xy' days to complete the work.
So if there were 'z' men, the total no. of days they would take to finish the work would be =
Applying the same concept, since 10 men take 6 days to complete the work, 1 man would take 10×6 = 60 days to complete the work.
So for 30 men, no. of days required = = 2 days to finish the work