if 10 men can do a work in 12 days,how many men can do the work in 8 days
Answers
Answered by
1
15 men can do a work in 8 days
MSK95:
will you pls explain me
Answered by
2
there are 12 days take 10 men for do a work
so, 1 day take 12x10 men for do a work
and 8 day take 120/8 men for do a work
= 120/8
= 15 men ans
so, 1 day take 12x10 men for do a work
and 8 day take 120/8 men for do a work
= 120/8
= 15 men ans