if 10 men can do a work in 16 days and 8 men in 16 days what is the percentage increase in the number of days

Answers

Answered by TigerMan28
0

Answer:20% increase

Step-by-step explanation:

In 1st case =16*10=160

In 2nd case =8*16=128

% increase =

100-(128*100/160)

100-(8*10)

100-80

20% increase

Answered by shwetaahujatr
1

Answer:

Step-by-step explanation:

if 10 men do it in 16 days

then

1 man does work in = 16/10

8 men should have done =16/10*8=64/5 days i.e. 12.8

they have done it in 16 days

percentage increase =( 42/10 )/16*100

=105/4=26.25%

If right then please send a thanks, if wrong then please comment and tell the mistake .