If 10 men do a piece of work in 4 days. How manny men will be required to get same work done in 10 days
Answers
Answered by
10
Answer:
4 men's..
Step-by-step explanation:
1 day = 4/10
1 day = 2/5
10 days = 2/5*10
10 days = 4 men
Good morning ....
hope it will help you..
Please drop some thanks
Answered by
3
Answer:
10 men-----4 days
? men-----10days?
in 1 day, no. of men=4/10
so, in 10 days, no of men=(4/10)*10=4
so, in ten days, 4 men do the work.
Hope it helps!!!