Math, asked by vgandhi1976, 1 year ago

if 10 men will take 6 days to construct a wall, then how many more men are needed if wall is to be completed in 5 days .. please do the whole working fast

Answers

Answered by sirfria
1
Heya
Here’s your answer

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Work done in 6 days =1/6
Work done in 5 days =1/5

If 1/6 work s done by 10 men
Then 1 work is done by 10*6/1
Then 1/5 work is done by 10*6*1/5
= 12men


~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Hope it helps

sirfria: Plzzz mark brainliest