If 10 people working for 8 hours a day can complete a task in 24 days how many people working 10hours a day would be required to.Complete the same task in 16 days
Answers
Answered by
4
Answer : 12 men
Solution :
_________
Given that :
m1 = 10, h1 = 8 and d1 = 24
m2 = ?, h2 = 10 and d2 = 16
Here, w1 = w2
Let, m2 = x men
As we know that :
So, 12 men would be required to complete the work.
Solution :
_________
Given that :
m1 = 10, h1 = 8 and d1 = 24
m2 = ?, h2 = 10 and d2 = 16
Here, w1 = w2
Let, m2 = x men
As we know that :
So, 12 men would be required to complete the work.
Similar questions
Math,
6 months ago
Computer Science,
6 months ago
Science,
6 months ago
Math,
1 year ago
Math,
1 year ago
Social Sciences,
1 year ago
Biology,
1 year ago