If 100 men can do 100 jobs in 100 days, then
1 man can do one job in:
Answers
Answered by
4
Step-by-step explanation:
i think that you satisfied with this answer.
Attachments:
Answered by
9
Answer:
100 days
Step-by-step explanation:
100 men can do 100 jobs in 100 days
100 men can do 1 job in 1 day.
Therefore, work done by one man, = 1/100 of 1 job
So one complete job will be completed in 100 days.
Hope this helps :)
Hope this helps :)please mark me as Brainliest