If 12 machines 7 hours a day can finish a work in 18 days. In how many days will 16 machines working 9 hours a day finish twice the work?
Answers
Answered by
1
21 days
Solution:-
let total number of days be x for finish.
machines hours days. quantity
(↓). (↓). (↑). (↑)
12 7 18 1
16. 9. x. 2
________________________________
x/18 = (12/16)×(7/9)×(2/1)
x = (12×7×2×18) / (16×9×1)
= (3×7×2×2) / ( 4×1)
= 3×7
= 21 days
Therefore the number of days = 21 days