if 12 men and 16 boys can do a piece of work in 5 days and, 13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it..
no wrong answer...
pls explain the process.
Attachments:
Answers
Answered by
0
Step-by-step explanation:
5(12 M + 16 B) = 4(13 M + 24 B)
60M + 80B = 52M + 96B
That gives, 8M = 16B, which is , 1M=2B
Now, 12 M + 16B can do work in 5 days.
So, 12 M + 8 M can do work in 5 days.
So, 20M can do work in 5 days.
Now, 7M + 10B = 7M + 5M = 12 M
Hence, if 20M can do work in 5 days, 12M can do work in (20*5)/12 = 8.33 days.