If 12 men and 16 boys do a piece of work in 15 days and, 13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it
Answers
Answered by
1
Answer:
this is the ans....
Step-by-step explanation:
SOLUTION:−
2:5=4:x
2/5=4/x
2x=4 X 5
2x=20
x=10
4. Here 4 kg =40 r.
hence 1 kg = 10r.
therefore 6 kg = 10X6 = 60r.
☺Hope this helps you☺