if 12 men can dig a pond in 8 days .How many men can dig in 6 days ?
Answers
Answered by
6
12 men working 8 days to dig a pond=96 man-days
working 6 days to dig the same pond will require 96/6=16 men
working 6 days to dig the same pond will require 96/6=16 men
Answered by
3
Answer:
16 men is answer .