Math, asked by raviy, 1 year ago

if 12 men can dig a pond in 8 days .How many men can dig in 6 days ?

Answers

Answered by Deepmala8
6
12 men working 8 days to dig a pond=96 man-days
working 6 days to dig the same pond will require 96/6=16 men
Answered by kumarivandana
3

Answer:

16 men is answer .

I hope it's help you .❤✌

plz mark me as a brainliest

And also thanks on my this answer.