Math, asked by ROOTVI, 1 year ago

If 12 men or 18 women can complete a piece of work in 7 days in how many days can 4 men and 8 women complete the same work ?

Answers

Answered by akhilkick
2
given,
18 women can complete work in 7 days
sowork done by 1 women=7/18
similarly, work done by1 men=7/12
 also given,
                  4 men and 8 women complete the same work                        so,   =(4×7/12) + (8×7/18)
                               =21+(28/9)
                               =(189+28)/9
                               =217/9
therefore your answer is 217/9 days