if 14 workers can make a machine in 45 hours how many workers will be required to complete the job in 35 hours
Answers
Answered by
12
Answer:
18 workers
Step-by-step explanation:
Total work = 45×14 manhrs
Workers required to finish in 35 hrs =
45×14/35
= 9×14/7
= 9×2
= 18
amitnrw:
Pls mark brainliest if it helps
Answered by
9
1 one worker completes the work by 45/ 14 hours
X workers complete the work by 35 h
X =45 x14/35
= 18 workers
Mark me brainliest pleeeeeeeese
X workers complete the work by 35 h
X =45 x14/35
= 18 workers
Mark me brainliest pleeeeeeeese