if 15
can do a piece of work in 14 days, in how many days can 7men do it
Answers
Answered by
0
Answer:
30 days
Step-by-step explanation:
Multiply 15 and 14.
Divide them by 7
you will get your answer.
Answered by
1
15×14=210
then divide by 7
210/7=30
please mark as brainliest