If 15 men completes a work in 27 days and same work 13 women completes in 30 days. then if they work combine but after 3 days of starting one man left the work, next day one woman left the work again next day one man left the work and so on. so how many days will it be taken to complete this work?
Answers
Answer:
10 days approx
Step-by-step explanation:
Given ,
15 Men complete work in 27 days,
13 Women complete same work in 30 days.
Now,
consider that work is = X = 100;
We will calculate how much work 1 Men and 1 Women is doing in 1 day.
so 1 Men will do x work in 1 day is
x1 = (X/27)/15
x1=(100/27)/15
x1=0.2469 ...(1)
likewise for woman,
x2= (X/30)/13
x2=(100/30)/13
x2=0.2564 ...(2)
If they combine there work together then 1 Men and 1 Women will do work
is x3=[(X/27)/15] + [(X/30)/13]
x3=0.2469 +0.2564
x3=0.5033 ...(3)
Now, they work together continually only for 3 days, with 15 Men and 13 Women
So, work done in 3 days is
=[ (x1 * 15) + (x2*30)] * 3 ..... by (1) and (2)
=[ (0.2469 * 15) + (0.2564 * 30) ] * 3
=[11.1486] *3 ...(4)
=34.1865 ... (5)
Now , On day 4 one men left,
So work done on day 4 is
=11.3955 - 0.2469 ... by (4)
=11.1486 + 34.1865 ...by (5)
=45.3351
Now day 5 ,
=45.3351 + [ 11.1486 - 0.5033]
=45.3351 +[10.6453]
=55.9804
Now day 6,
=55.9804 +[10.6453 - 0.2469 ]
= 55.9804 + 10.3984
=66.3788
Now day 7,
= 66.3788 + [10.3981 - 0.2564]
= 66.3788 +[10.1417]
= 76.5205
Now day 8,
= 76.5205 + [10.1417 - 0.2469]
= 76.5205 + [9.8948]
= 86.4153
Now day 9,
= 86.4153 + [9.8948 - 0.2564]
= 86.4153 + [9.6384]
= 96.0537
Now day 10
= 96.0537 + [9.6384 - 0.2469]
= 105
So combine they will take approx 10 days to complete the task.