Math, asked by nandarenoy, 1 month ago

If 15 workers can finish a task in 40 days, calculate the number of workers

required to complete the same task in 25 days.

plss answer​

Answers

Answered by saiaadityabaday
0

Answer:

Step-by-step explanation:

15 workers - 40 days                                              

? workers - 25 days

15*42 30*x

630 30*x

x = 630/30

21