If 16 men working 7 hours a day can plough a field in 48 days, in how many days will 14 men working 12 hours a day plough the same field?
Answers
Answered by
7
Answer:
Number of man- hours required to plough the field= 16 x 7 x 48- man- hours.
So number of days required to plough the field with 14- men working 12- hours a day
= (16 x 7 x 48) ÷ (14 x 12)
= 32 days.