If 18 men can do a piece of work in 50 days , in how many days will 15 men do it ?
Answers
Answered by
4
ʜᴇʀᴇ's ʏᴏᴜʀ ᴀɴsᴡᴇʀ
ᴍᴀʀᴋ ᴍᴇ ᴀs ʙʀᴀɪɴʟᴇsᴛ
..........................................
Attachments:
Answered by
1
no. of days required for 15 men=50/15×18
= 50/5×6
= 10×6
= 60