If 1800 person can finish the construction of a building in 40 days, how many person are needed for the construction of the building in 24 days

Answers

Answered by sudu06
13

Answer:

1800 ppl------ 40 days

how many? -------- 24 days

since they are inversely proportional,

no. of ppl required = 1800×40/24

= 300×10

= 3000 ppl

hence ur answer is 3000 persons