Math, asked by sanjma, 1 year ago

if 20 men can finish a piece of work in 20 days in how many days can 25 men do it​

Answers

Answered by llllll4
2

Answer:

20 multiply 20 divided by 25

Answered by karthik961
1

Men and days are in direct proportion..

if men power increases, no of days work complete decreases..hence

M1D1=M2D2

(20)(20)=(25)D2

D2=16 days