if 20 men working together can finish a job in 20 days the number of days taken by 25 men of the same capacity​

Answers

Answered by jhamani1975
3

Answer:

Step-by-step explanation:

20 men can finish the work in 20 days

1 man will complete the work in 20 ×20 days

25 men will complete the work in = (20×20)/25

= 16 days