if 20 workers can do two third of a piece of work in 50 days then what fraction of the work can be done by 12 workers in 60 days
Answers
Answered by
0
Answer:
The answer is 6/25
Step-by-step explanation:
20 men complete one-third of a work in 50 days
Part of work completed by 20 m in 50 days = (1/3)
Part of work completed by 20 m in 1 days = (1/3)(1/50)
Part of work completed by 1 m in 1 days = (1/3)(1/20)(1/50) = (1/3000)
then,
Part of work completed by 12 m in 1 days = (1/3000)*12 = (1/250)
Part of work completed by 12 m in 60 days = (1/250)*60 = (6/25)