if 21 workers built a wall in 7 days,how many workers will be required for the same work to be completed in 3 days​

Answers

Answered by Himanshi36621
1

Answer:

9 is the answer

Step-by-step explanation:

First we need to find how many workers will built a wall in 1 day for that you have to divide 21 by 7 you will get 3 now you can multiply 3 by 3 and then you will get the answer