Math, asked by kammarichandu285, 9 months ago

if 24 men can do a piece of work in 35 days in how much days will 42 men do the same work​

Answers

Answered by kabir6822
0

Answer:

20 days

Step-by-step explanation:

case of inverse proportion

24 × 35/ 42

= 20 days

Similar questions