If 25 men can dig a canal of length 62.5 m in 40 days, how many men will be required to
dig a similar canal of length 155 m in 40 days?
[HINT: Since the number of days is same in both cases, it has no effect on the calculations.]
Answers
Answered by
12
Answer:
Step-by-step explanation:
Secondary School Math 5+3 pts
If 25 men dig a canal length 62.5m in 40 days how many men will be required to dig a similar canal of length 155 m in 40 days.
Report by Naveen8481 21.12.2018
Answers
The Brain
THE BRAINLIEST ANSWER!
TheMahakals
TheMahakals Maths AryaBhatta
Solutions :-
Given :
25 men dig a canal length 62.5 m in 40 days.
Let the x men are required to dig a similar canal of length 155 m in 40 days.
According to the question,
=> 25/62.5 = x/155
=> 25 × 155 = x × 62.5
=> 3875 = 62.5x
=> 3875/62.5 = x = 62
Hence,
62 men are required to dig a similar canal of length 155 m in 40 days.
Answered by
2
Answer:
62
Step-by-step explanation:
25*40 M*40
---------- = ---------
62.5 155
M = 155*25/62.5 = 62