If 25 workers can finish a job in 40 days, how many workers will complete the same job in 25 days?
Answers
Answered by
91
Hi there !
_____________________
Given :
25 workers can finish a job in 40 days.
To find :
The number of workers to complete the same job in 25 days.
Solution :
In 40 days, no of workers required to complete the job = 25
In 1 day, no of worker required to complete the job = 25 × 40
In 25 days, no of workers required to complete the job = 25 × 40 / 25
=> 40 workers.
Hence,
40 workers are required workers complete the same job in 25 days.
_____________________
Thanks for the question !
☺☺☺
_____________________
Given :
25 workers can finish a job in 40 days.
To find :
The number of workers to complete the same job in 25 days.
Solution :
In 40 days, no of workers required to complete the job = 25
In 1 day, no of worker required to complete the job = 25 × 40
In 25 days, no of workers required to complete the job = 25 × 40 / 25
=> 40 workers.
Hence,
40 workers are required workers complete the same job in 25 days.
_____________________
Thanks for the question !
☺☺☺
Attachments:
Answered by
36
here is your answer OK
Total Work = Number of workers * number of days = 25 * 40= 1000 units
so we divide by 25
1000/25 = 40 days
Total Work = Number of workers * number of days = 25 * 40= 1000 units
so we divide by 25
1000/25 = 40 days