If 3/5 part of a work is done by 12 men in 10 days,
how many men will complete the whole work in 20
days?
168
10
Answers
Answered by
8
Work = no. of men × no. of days
3/5 = 12×10
3/5 = 120
3 = 600
200 units
hence 200 units of work done in 10 days by 12 men.
now, we have to find the no. of men complete the total work in 20 days.
so,
no of men = 200/20 = 10 men
hence, 10 men complete the whole work in 20 days.
Hope it helps.