If 30 labourers working 7 hours a day can finish a piece of work in 18 days, how many labourers working 6 hours a day can finish it in 30 days?

Answers

Answered by edenangel04
5

Answer:

44 labourers

Step-by-step explanation:

We will use Chain Rule to solve this question.

According to Chain Rule, the work efficiency remains constant.

WWF×T= Constant

Here W = Work Done, WF = Workforce, T = Time.

Let the number of workers needed be 'x'.

Applying Chain Rule,

W30×24×6=Wx×20×5

Or, x=43.2 Workers (Answer)