Math, asked by naman620, 11 months ago

if 30 men do 1/7 of a job
part in 2 days how many days will 21 men take to do the work​

Answers

Answered by sahilsinghpradhan444
18

Step-by-step explanation:

30 men do 1/7 part of the work in 2days

1 men do 1/7partof work in 30×2 days

21 men do 1/7 part of work in (30×2)/21 days

So

1/7 part of work done by 21 men in (30×2)/21days

1part of work done by 21 men in {(30×2)/21}×2=20 days

SO 21 MEN COMPLETE FULL WORK IN 20 DAYS AND THE 1/7 th PART OF THE TOTAL WORK IN {(30×2)/21} DAYS