if 36 men can do a piece of work in 25 days then how many days will 15 men complete the same work.please answer
Answers
Answered by
0
Given that
36 men can do piece of work in 25 days
To find
How many days will require to 15men to complete same piece of work
Solution
As per given condition
Let x as the days require to 15men to complete same piece of work
from above two equation
by multiplication we get
Hence 15 men require 60 days to complete same piece of work.