if 36 men finish a piece of work in 25 days how many days will 15 men take to do it
Answers
Answered by
1
Answer:
men. Days
36. . 25
15. X?
36 x 25/15=60
60 days
Answered by
0
36 men take time=25days
15 men take time=36/25x5
=60 days