Answer:
yha m mtlb man d1 mtlb day or W mtlb wprk h
Attachments:
Answered by
2
Answer: 9 People (C)
Explanation:-
Remaining work =1/4
Remaining time = 8 days
Remaining time = 8 daysWork done by 36 persons in 1 day =1/40
Work done by 1 person in 1 day =1/36×40
Let the number of persons required to finish the remaining work be 'x'
Let the number of persons required to finish the remaining work be 'x'8×X×1/36×40=1/4
Or,X = 45
Number of additional persons required=45-36=9.