If 36 persons are engaged on a piece of work, the work can be completed in 40 days. After 32 days, only 3/4 th of the work was completed. How many more persons are required to complete the work on time?
A)10
B)8
C)9
D)12

Answers

Answered by iashuboy94
4

Answer:

yha m mtlb man d1 mtlb day or W mtlb wprk h

Attachments:
Answered by junaid629577
2

Answer: 9 People (C)

Explanation:-

Remaining work =1/4

Remaining time = 8 days

Remaining time = 8 daysWork done by 36 persons in 1 day =1/40

Work done by 1 person in 1 day =1/36×40

Let the number of persons required to finish the remaining work be 'x'

Let the number of persons required to finish the remaining work be 'x'8×X×1/36×40=1/4

Or,X = 45

Number of additional persons required=45-36=9.