If 4(four) workers complete a piece of work in 20 days and 2(two) workers
complete the same work in y days then y is equal to
A.10
B.40
C.30
None of the above is true.
plz help me with this !!!!
Answers
Answered by
0
Answer:
- 40days
Step-by-step explanation:
As we know that,
4 workers complete a work in 20 days
So,
1 workers complete a work in 20×2 days
So,
2 workers complete a work in (20×2)/2 days
SO, Number of Day = (20×2)/2 = 40
So, the value of y = 40