If 4 men and 5 women can do a piece of work in 50 days where as 7 men and 13
women can do the same piece of work in 28 days, how long will 10 men and 6
women take to do the same piece of work?
please help me to do this sum..
Its very urgent..
Answers
Answered by
1
Answer:
20.4
Step-by-step explanation:
(4M + 5W )×50/1 = (7M + 13W)×28/1
(4M + 5W)25 = (7M + 13W)×14
2M = 57W => M/W = 57/ 2
total work
=[ 4(57) + 5(2)] ×50 = 11900 units
(10M + 6W)'s 1 days' work
= 10(57) + 6(2) = 582 units
so (10M + 6W) can do the same work in
= 11900/582 = 20.4 days