if 40 men can finish a piece of work in 60 days in how many days will 75 men finish the same work
Answers
Answered by
158
See,
40 mens can do the work in 60 days.
then
1 men can do the same work in = 40×60 days
=2400days
then we can find the no. of days required to finish the same work by 75 mens
=2400/75
=32days.
40 mens can do the work in 60 days.
then
1 men can do the same work in = 40×60 days
=2400days
then we can find the no. of days required to finish the same work by 75 mens
=2400/75
=32days.
pinkuu1:
thank u
Answered by
2
75 men finish the same work in 32 days.
Given: 40 men finish a work in 60 days and and then number of men increased to 75.
To Find: Days taken by 75 men to complete the work
Solution:
Initial number of men is 40
Days taken by thm to complete work = 60
Final number of men = 75
Then, M₁ × D₁=M₂ × D₂
40 × 60 = 75 × D₂
D₂ = 32 days
Hence, there are 32 days taken by 75 men to complete the work.
#SPJ3