If 40 workers can do a job in 15 hours, how many workers will be required to do the same job in 8 hours?​

Answers

Answered by meherg21
3

Answer:

75

Step-by-step explanation:

Let

worker = x

worker : hours

40:x. : 15:8

x/40 = 15/8

x= 1.875*40

x=75