Math, asked by ikkuhuzzi, 5 days ago

if 45 men can do a piece of work in 49 days. in how many days will 35 men do it? if the work is to be completed in 9 days how many men will be required to work?​

Answers

Answered by vedanthd4611
2

Answer:

(45×49) ÷ 35 you can get your ans

Step-by-step explanation:

plz mark me as brainlist

Answered by danishmumtaz
2

Answer: 63,245

Step-by-step explanation:

(i) (49*45) / 35 days = 63 days.

(ii) 49*45/9=245 men

   