If 45 men can do a piece of work in 49 days then how many days will it require by 35 men to do the same work
Answers
Answered by
6
I think this is Correct
Attachments:
Answered by
5
HI HERE UR ANSWER
●●●●●●●●●●●●●●
TIME TAKEN BY 45 MEN=49days
TIME TAKEN BY 1 MAN
◆◆◆◆◆◆◆◆◆◆◆◆◆◆
=45×49
=2205days
NOW TIME TAKEN BY 35 MEN WILL BE=
●●●●●●●●●●●●●●●●
TIME TAKEN BY 1 MAN ÷NO. OF MAN
=2205/35
=63 days
SO,TIME TAKEN BY 35 MAN IS 63 DAYS.
☺️☺️☺️☺️☺️☺️☺️☺️☺️