if 48 men can dig a trench in 14 days , how long will 28 men take to dig a similar trench ​

Answers

Answered by aviralkachhal007
12

\huge{\mathfrak{\red{\boxed{\green{\underbrace{\overbrace{\blue{†Answer†}}}}}}}}

48 men can do work in 14 days

So, 28 men will do in

28 \times  \frac{48}{14}

2 \times 48

96

Please give me 10 thanks.......

Answered by akshu97333
1

Answer:

24

Explanation:

rom the question,

48 men can dig a trench in 14 days

1 man can dig a trench in =(14×48) days    .. [ less men, more days]

∴28 men can dig a similar trench in =(14×48)/28

=24 days   ...[ More men, less days]

Hence, the required number of days for 28 men to dig a trench =24.